Non-Compliance detail


  
Summary
 
Licence number: 227
Annual Return Start: 01 Jan 2006
Annual Return End: 31 Dec 2006
Date Received: 01 Mar 2007
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2.1 Non-compliance with Special Frequency 1 monitoring and sampling requirements (which requires the collection of samples within 24 hours of a discharge occurring) for Discharge Point 1 (overflow from pond 3 weir) on one occasion (10 Sepetmeber 2006). Appropriate Action taken by licensee 1
M2.1 Weekly monitoring and sampling frequency for Discharge Point 3 was not complied with on two occasions. On 11 January 2006 samples were collected but not all analytes tested. On 12 July 2006 the treatment plant was shut down for maintenance. Appropriate Action taken by licensee 2